Sunday, January 29, 2012

Electric, Painting, Etc

Definite progress here. Even delivered the cabinets for the island in the kitchen.  First coats of paint are on, but not the final.  
Nice looking trim work going in now.
We will probably clean before the floors are installed.
Stay tuned!



Saturday, January 14, 2012

Progress 14 January

The mud and tape work looks about done.  And I believe the cement work is about complete too.  90-14 >> about 76 days!  Getting there quickly now! 




Clean Sweep

Ah, the diligent workers.  Thank you!!  You got the place cleaned up nicely last weekend.


Sunday, January 1, 2012

Much drywall has been hung - about half.
Floor sweeping next Sunday will include more mess from hanging, taping, mudding, etc.  Exciting stuff!