I have 9 of us signed up for cleaning on Saturday. We can put some more able bodies to work cleaning the concrete so that the tile floors can go in well next week. Please send me a note or comment here if you can help out. We need brooms, shop vacuums, industrial mops, water (it is not on yet in the building) and your energy!
Thanks!
UUFF Chalice Circle Construction Progress
Tuesday, February 14, 2012
Sunday, February 5, 2012
Still wet in early Feb
Still too much rain. Do the "no rain" dance, if you can.
The trim is up. Final paint will be before you know it!
The kitchen is shaping up nicely (on a shoestring.)
Sunday, January 29, 2012
Electric, Painting, Etc
Definite progress here. Even delivered the cabinets for the island in the kitchen. First coats of paint are on, but not the final.
Nice looking trim work going in now.
We will probably clean before the floors are installed.
Stay tuned!
Saturday, January 14, 2012
Progress 14 January
The mud and tape work looks about done. And I believe the cement work is about complete too. 90-14 >> about 76 days! Getting there quickly now!
Sunday, January 1, 2012
Friday, December 30, 2011
Ready for Drywall
Drywall starts tomorrow! Yay!
Check out the stage, folks.
Cleaning tentatively scheduled for 8 January.
Cleaning tentatively scheduled for 8 January.